Verified C-TS412-1909 Exam Dumps Q&As - Provide C-TS412-1909 with Correct Answers [Q14-Q38]

Share

Verified C-TS412-1909 Exam Dumps Q&As - Provide C-TS412-1909 with Correct Answers

Pass Your C-TS412-1909 Dumps Free Latest SAP Practice Tests


SAP C-TS412-1909 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Reporting < 8%

Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports

Cost and Budgets > 12%

Describe procedures for establishing budgets and reporting costs.

Project Structures > 12%

Name the components of Work Breakdown Structure, Network and activities, Milestones

Dates > 12%

Describe the importance of various dates which can be tracked for projects

Revenues and Payments > 12%

Describe the characteristics of Revenues & Payments.

Resources > 12%

Describe how the Resource Planning process integrates with HCM


 

NEW QUESTION 14
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.

  • A. Basic dates for activities
  • B. Internally processed activities
  • C. Document information records
  • D. Relationships
  • E. Material components

Answer: B,D,E

 

NEW QUESTION 15
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

  • A. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
  • B. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
  • C. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
  • D. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.

Answer: D

 

NEW QUESTION 16
Where do you control whether a project stock is managed as valuated or non-valuated project stock?

  • A. In the project definition
  • B. In the network activity
  • C. In the WBS element
  • D. In the material master

Answer: A

 

NEW QUESTION 17
How are earliest dates and latest dates of activities scheduled?

  • A. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.
  • B. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.
  • C. Earliest dates and latest dates are scheduled by forward scheduling.
  • D. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.

Answer: B

 

NEW QUESTION 18
In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

  • A. Control key of an activity
  • B. Scheduling and distribution key
  • C. Capacity planner group in the network header
  • D. Scheduling and capacity category

Answer: A

 

NEW QUESTION 19
When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.

  • A. Service purchase order number
  • B. Material master within service specification
  • C. Vendor
  • D. Service specification
  • E. Overall limit (maximum value of all unplanned services)

Answer: C,D,E

 

NEW QUESTION 20
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct Answers to this question.

  • A. If the maximum reduction level is less than 100
  • B. If the reduction strategy is set in each activity
  • C. If the appropriate reduction type is set in the parameters for network scheduling
  • D. If the reduction strategy is set in the network header

Answer: C,D

 

NEW QUESTION 21
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.

  • A. Third-party order
  • B. Preliminary purchase requisition for WBS element
  • C. Planned order
  • D. Purchase requisition and Reservation for WBS element
  • E. Reservation for WBS element

Answer: B,D,E

 

NEW QUESTION 22
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.

  • A. Controlling area
  • B. Operating concern
  • C. Company code
  • D. Plant
  • E. Sales organization

Answer: A,C,D

 

NEW QUESTION 23
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.

  • A. Multiple project simulations can be used simultaneously.
  • B. Project simulations allow posting of actual data.
  • C. Project simulations can create purchase requisitions.
  • D. Project simulations can be used to plan structures and costs.
  • E. Project simulations can be created without using an operational project as a template.

Answer: A,D,E

 

NEW QUESTION 24
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.

  • A. Project versions are mandatory for Milestone Trend Analysis (MTA).
  • B. Project versions can be changed.
  • C. Project versions can be created automatically based on user status.
  • D. Manually created project versions always require a project version profile.

Answer: A,B

 

NEW QUESTION 25
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.

  • A. The material master of the component must permit project stock management.
  • B. The network is assigned to a sales order item.
  • C. The network activity is assigned to a WBS element.
  • D. A procurement indicator must be assigned to the activity.
  • E. The Project Stock indicator is set in the project definition (non-valuated or valuated).

Answer: A,D,E

 

NEW QUESTION 26
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?

  • A. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
    -> Purchase order monitoring -> Goods receipt -> Invoice receipt
  • B. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
  • C. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
  • D. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval

Answer: D

 

NEW QUESTION 27
Which report can use user-specific layouts?

  • A. Cost element report
  • B. Line item report
  • C. Hierarchical report
  • D. Enhanced individual overview

Answer: B

 

NEW QUESTION 28
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?

  • A. Network profile
  • B. Parameters for the network type
  • C. Network type
  • D. Project profile

Answer: B

 

NEW QUESTION 29
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.

  • A. A dynamic item processor (DIP) profile with the appropriate settings
  • B. An activity-account-assigned network that is assigned to a sales order item
  • C. A header-account-assigned network that is assigned to a sales order item
  • D. Released WBS elements, activities, and/or activity elements

Answer: A,D

 

NEW QUESTION 30
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

  • A. Activity
  • B. Milestone
  • C. Activity element
  • D. Network header

Answer: A

 

NEW QUESTION 31
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.

  • A. Milestone trend analysis
  • B. Results analysis
  • C. Settlement
  • D. Confirmations
  • E. Progress analysis

Answer: B,C,E

 

NEW QUESTION 32
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.

  • A. The formula for costing in the work center is incorrect.
  • B. Integrated planning for the network is active.
  • C. The duration is missing in the activity.
  • D. The Determine Costs indicator in the network header rules out planned cost calculation.
  • E. The activity output price for the activity type and cost center assigned to the work center is not maintained.

Answer: C,D,E

 

NEW QUESTION 33
Where do you maintain the length of the project ID?

  • A. Project type
  • B. Project profile
  • C. Special characters
  • D. Project coding mask

Answer: D

 

NEW QUESTION 34
You want to assign milestones to WBS elements. For what can you use these milestones? Note: There are 2 correct Answers to this question.

  • A. To start workflow tasks
  • B. To set an actual finish date for WBS elements
  • C. To transfer the actual date to the billing plan
  • D. For trend analysis

Answer: C,D

 

NEW QUESTION 35
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.

  • A. Project definition
  • B. Sales order items
  • C. WBS elements
  • D. Milestones

Answer: B,C

 

NEW QUESTION 36
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?

  • A. Schedule line category
  • B. Item category
  • C. Requirements type
  • D. Requirements class

Answer: B

 

NEW QUESTION 37
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?

  • A. Set up the requirement date manually as February 5.
  • B. Set up the requirement date aligned with the activity start date and an offset of 5 days.
  • C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
  • D. Set up the requirement date aligned with the activity finish date and an offset of 15 days.

Answer: B

 

NEW QUESTION 38
......


C-TS412-1909 Exam Certification Details:

Level:Associate
Sample Questions: SAP C-TS412-1909 Exam Sample Question
Exam:80 questions

 

Get Top-Rated SAP C-TS412-1909 Exam Dumps Now: https://testinsides.actualpdf.com/C-TS412-1909-real-questions.html