NEW QUESTION 27
Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.
- A. You can create a project based on a Activity.
- B. You cannot use the characteristics of both the structures (WBS and Networks) together to represent a project.
- C. You can map a project using only one WBS or one network.
- D. You can also represent a project using a WBS and one or more networks.
Answer: C,D
NEW QUESTION 28
Material
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
- A. Immediately, by saving the project
- B. Automatically, using the requirement date and the replenishment lead time
- C. Using a standard milestone activity
- D. When releasing a network or an activity
Answer: B,D
NEW QUESTION 29
Resources
How are capacity requirements determined?
- A. Independent of scheduling and according to the capacity planner group.
- B. Using the control key of an activity.
- C. Using scheduling and the capacity category.
- D. Using scheduling and distribution key.
Answer: D
NEW QUESTION 30
Which report can use user-specific layouts?
- A. Line item report
- B. Cost element report
- C. Hierarchical report
- D. Enhanced individual overview
Answer: A
NEW QUESTION 31
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.
- A. Reservation for WBS element
- B. Preliminary purchase requisition for WBS element
- C. Purchase requisition and Reservation for WBS element
- D. Planned order
- E. Third-party order
Answer: A,B,C
NEW QUESTION 32
Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.
- A. Sales prices are maintained in the DIP profile
- B. Usage of cost elements is mandatory
- C. DIP is used to create a quotation
- D. Material determination is mandatory
- E. Sources can be based on line items
Answer: B,C,D
NEW QUESTION 33
Which object is relevant in assembly processing to create an assembly order for the SD document?
- A. Project profile
- B. Item category
- C. Control key
- D. Requirement class
Answer: A
NEW QUESTION 34
Which object is used to allocate the costs from a claim to the project structure?
- A. Claim
- B. WBS element
- C. Network activity
- D. Internal order
Answer: D
NEW QUESTION 35
Project Structure
Which statement regarding the creation of a new work breakdown structure (WBS element) are true?
Note : there are 3 correct answer for this question.
- A. You can create several WBS elements per level.
- B. The WBS structure can contain several level 1 WBS element, (es configurable por perfil de proyecto)
- C. A new work breakdown structure must contain up to 10 levels.
- D. A WBS element of the new project can be assigned to a different project definition.
- E. WBS element can be a planning element, an account assignment element, and a billing element at the same time.
Answer: A,B,E
NEW QUESTION 36
Materials
Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO).
- A. With delivery from projects you can generate purchase requisitions for sub-contractors.
- B. With delivery from projects You can generate goods issues for project without creating delivery documents.
- C. With the delivery from project you can deliver material component assigned to your network.
- D. With delivery from projects good receipt are automatically posted while saving.
Answer: B
NEW QUESTION 37
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20.
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?
- A. Set up the requirement date manually as February 5.
- B. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
- C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days
- D. Set up the requirement date aligned with the activity start date and an offset of 5 days
Answer: C
NEW QUESTION 38
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.
- A. Purchase order items
- B. Sales order items
- C. Internal orders
- D. Reservations
Answer: A,D
NEW QUESTION 39
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity.
What controls whether the delivery date is defined by the earliest or latest scheduled dates?
- A. The table of MRP controllers
- B. The scheduling parameters for the network
- C. The control key
- D. The network profile
Answer: B
NEW QUESTION 40
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question
- A. A bill of material with sales views
- B. A production order
- C. Assignment between material and standard network
- D. Standard network with activities
- E. A material master with sales views
Answer: C,D,E
NEW QUESTION 41
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are
3 correct Answers to this question.
- A. Confirm production order
- B. Stock transfer posting
- C. Cancel goods issue
- D. Generate delivery
- E. Generate purchase requisition
Answer: B,D,E
NEW QUESTION 42
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.
- A. Planned revenue requires a sales order assigned to a WBS element.
- B. Planned revenue can be transferred from a sales quotation.
- C. Actual revenue is posted via a billing plan assigned to a WBS element.
- D. Actual revenue is posted via a billing document created from a sales order
Answer: B,D
NEW QUESTION 43
You want to assign milestones to WBS elements. For what can you use these milestones? Note: There are 2 correct Answers to this question.
- A. For trend analysis
- B. To set an actual finish date for WBS elements
- C. To transfer the actual date to the billing plan
- D. To start workflow tasks
Answer: A,C
NEW QUESTION 44
Which objects can be used to specify settlement rules? Note: There are 2 correct answers to this question?
- A. Network activity for activity-account-assigned networks
- B. Network header for activity-account-assigned networks
- C. WBS elements
- D. Standard WBS elements
Answer: A,C
NEW QUESTION 45
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.
- A. Easy Cost Planning
- B. Project planning board
- C. Project Builder
- D. Schedule Manager
Answer: B,C
NEW QUESTION 46
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.
- A. Whether the work for the internal activity is greater than its duration
- B. The factory calendar in the work center used for the internal processing activity
- C. An activated Scheduling indicator in the control key of the internal processing activity
- D. The unit (for example, hour, day) of the field Normal Duration field of the activity
- E. The relationships between activity elements
Answer: B,C,E
NEW QUESTION 47
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question
- A. A shipping point is necessary
- B. A sales order must be created in advance
- C. A sold to party is necessary
- D. A delivery document type must be configured
Answer: A,D
NEW QUESTION 48
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.
- A. Resource reports
- B. Structure information system reports
- C. Cost element reports
- D. Hierarchical reports
Answer: B
NEW QUESTION 49
......
SAP C-TS412-1909 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Cost and Budgets > 12% | Describe procedures for establishing budgets and reporting costs. |
| Reporting < 8% | Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports |
| Project Structures > 12% | Name the components of Work Breakdown Structure, Network and activities, Milestones |
C-TS412-1909 Dumps 100 Pass Guarantee With Latest Demo: https://testinsides.actualpdf.com/C-TS412-1909-real-questions.html