NEW QUESTION 88
Which is one of the three levels of plan in PRINCE2?

  • A. Programme Plan
  • B. Benefits Review Plan
  • C. Team Plan
  • D. Project Brief

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 89
Why is the 'learn from experience' principle applied to a project?

  • A. To enable the project team to repeat successes from previous projects
  • B. To enable the project team to use tolerances to delegate authority
  • C. To enable the project team to develop a business case for the project
  • D. To allow the project to be divided into management stages

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://link.springer.com/chapter/10.1007/978-3-319-23000-9_4

 

NEW QUESTION 90
Which is a purpose of the Controlling a Stage process?

  • A. Select and implement actions that will resolve deviations from a plan within tolerance
  • B. Update a Project Plan to incorporate the actuals from a Stage Plan
  • C. Produce a Team Plan for the work to be assigned to a Team Manager
  • D. Obtain approvals for products delivered in a Work Package

Answer: A

 

NEW QUESTION 91
Which is a purpose of the Closing a Project process?

  • A. Confirm that all benefits defined in the Business Case have been achieved
  • B. Authorize the final stage of the project
  • C. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
  • D. Delegate day-to-day management of the end of the project to the Project Manager

Answer: C

 

NEW QUESTION 92
Which role is responsible for creating Checkpoint Reports?

  • A. Project Support
  • B. Senior Supplier
  • C. Change Authority
  • D. Team Manager

Answer: D

Explanation:
Section: Volume B

 

NEW QUESTION 93
Which statement describes the responsibilities of a risk actionee?

  • A. Carrying out a risk response action to respond to a particular risk
  • B. Managing, monitoring and controlling of all aspects of an assigned risk
  • C. Owning and authorizing the use of the risk budget to fund risk responses
  • D. Identifying risks to the project that might occur in their department

Answer: A

 

NEW QUESTION 94
How many management stages should a PRINCE2 project consist of?

  • A. Start up stage, initiation stage and a closing stage
  • B. Initiation stage and at least one other management stage to cover the remainder of the project
  • C. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
  • D. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 95
According to PRINCE2, which characteristic is necessary for an effective project board?

  • A. An ability to delegate
  • B. An attention to detail
  • C. A 'problem-solving' approach
  • D. A calm management style

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/project-board/

 

NEW QUESTION 96
Which is a step in the recommended approach to 'defining and analyzing the products'?

  • A. Writing a project product description
  • B. Identifying activities and dependencies
  • C. Designing a plan
  • D. Preparing estimates

Answer: C

Explanation:
Explanation
Reference http://prince2.wiki/Plans

 

NEW QUESTION 97
Which level of management sets the project level tolerances?

  • A. Project manager
  • B. Project board
  • C. Corporate, programme management or the customer
  • D. Team manager

Answer: A

Explanation:
Explanation
Reference http://prince2.wiki/Manage_by_exception

 

NEW QUESTION 98
What is a supplier of a PRINCE2 project responsible for?

  • A. Providing the project mandate
  • B. Realizing the benefits from the project
  • C. Establishing the project's governance
  • D. Providing resources to deliver the project outputs

Answer: D

Explanation:
Explanation
Reference http://prince2.wikidot.com/senior-supplier

 

NEW QUESTION 99
Which should be funded from a change budget?

  • A. A change to a plan, within allocated tolerances, due to poor estimating
  • B. An agreed change to the scope of a project
  • C. A fallback plan
  • D. The Starting up a Project process

Answer: B

 

NEW QUESTION 100
Which is a purpose of a project brief?

  • A. To provide a sound basis for project initiation
  • B. To define how the achievement of the project's benefits can be measured
  • C. To act as a base document which enables the project board to assess progress
  • D. To provide a description of the means and frequency of communication

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:http://www.prince2how2.com/2014/12/prince2-project-brief-template.html

 

NEW QUESTION 101
Identify the missing words in the following sentence.
The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

  • A. corporate, programme management or the customer have authorized a project
  • B. the project mandate has been approved by the project board
  • C. the project board has agreed the project strategies
  • D. the 'starting up a project' process is completed

Answer: D

Explanation:
Explanation
Reference https://www.siliconbeachtraining.co.uk/blog/prince2-directing-project-process-dp

 

NEW QUESTION 102
Which statement about stages is true?

  • A. Management stages should be of the same duration
  • B. The use of technical stages is mandatory
  • C. Management stages are driven by specialist teams
  • D. The use of management stages is mandatory

Answer: D

Explanation:
Section: Volume B
Explanation/Reference:

 

NEW QUESTION 103
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

  • A. Directing a project
  • B. Controlling a stage
  • C. Managing a stage boundary
  • D. Starting up a project

Answer: B

Explanation:
Explanation
Reference
https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage-process-in-p

 

NEW QUESTION 104
Which of the following statements about stakeholders are true?
1.Someone who thinks they will be affected by a project is a stakeholder on that project
2.Stakeholders may be internal or external to the corporate organization

  • A. Both 1 and 2 are true
  • B. Neither 1 or 2 are true
  • C. Only 2 is true
  • D. Only 1 is true

Answer: A

 

NEW QUESTION 105
Which role is responsible for appointing the senior user in a project that is independent from a program?

  • A. The executive
  • B. Corporate, program management or the customer
  • C. The project manager
  • D. Project assurance

Answer: B

Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-roles-and-responsibilities/

 

NEW QUESTION 106
Which characteristic distinguishes a project from regular business operations?

  • A. Incurs cost
  • B. Produces benefits
  • C. Manages stakeholders
  • D. Introduces business change

Answer: D

Explanation:
Section: Volume A
Explanation

 

NEW QUESTION 107
Which is a purpose of a quality register?

  • A. To record cross-references to issues relating to the quality of the products
  • B. To record the date a completed work package was received
  • C. To provide the status of quality activities carried out for completed products
  • D. To capture quality concerns about completed products

Answer: B

 

NEW QUESTION 108
Which does NOT reflect the PRINCE2 principle of continued business justification?

  • A. If a project can no longer be justified, it should be stopped
  • B. The business justification drives decision making
  • C. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
  • D. There must be a justifiable reason for starting a project

Answer: C

 

NEW QUESTION 109
Which is a purpose of a Lessons Report?

  • A. Improve the project management method for future projects
  • B. Provide a summary of the benefits realized during the project
  • C. Compare the actual performance of the final stage against its plan
  • D. Detail open issues and risks that need to be managed after the project has closed

Answer: A

 

NEW QUESTION 110
Which statement about applying the 'tailor to suit the project' principle is CORRECT?

  • A. The tailoring of PRINCE2 is MOST appropriate for agile projects
  • B. A technically complex project should NOT tailor PRINCE2
  • C. PRINCE2 can be tailored to be used with any type of project
  • D. A project which is part of a programme should NOT tailor PRINCE2

Answer: C

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Tailoring

 

NEW QUESTION 111
Which is a factor when deciding the duration of a management stage?

  • A. The level of risk in the project
  • B. The cost of the stage
  • C. The work packages to be delivered
  • D. The number of products to be produced in the project

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/the-design-of-prince2-management-stages/

 

NEW QUESTION 112
Which product records any project outcomes perceived as negative by stakeholders?

  • A. Project Product Description
  • B. Project Plan
  • C. CommunicationManagement Strategy
  • D. Business Case

Answer: D

 

NEW QUESTION 113
......

PRINCE2-Foundation Exam Questions Get Updated [2021] with Correct Answers: https://testinsides.actualpdf.com/PRINCE2-Foundation-real-questions.html